Projjex Ltd · Project Management, Planning & Forensic Planning Consultants
✉ hello@projjex.co.uk✉ hello@projjex.co.uk
Ordo is now liveInstant programme assurance - DCMA 14-point & CIOB PP21 scored in secondsUpload a P6, Asta or Excel programme, nothing to installFeasibility verdict & a Monte Carlo completion forecastTry Ordo free →
Ordo is now liveInstant programme assurance - DCMA 14-point & CIOB PP21 scored in secondsUpload a P6, Asta or Excel programme, nothing to installFeasibility verdict & a Monte Carlo completion forecastTry Ordo free →

Project Management & Recovery Case Studies

Selected engagements from across the UK water and infrastructure sectors - distressed project recovery, NEC delivery, compensation event strategy and multi-million pound claims, from £3m to £170m+.

Church Wilne (Green Recovery)

Severn Trent Water

ClientSevern Trent Water
Value£170m+
ContractNEC ECI
RolePM & Commercial

Early Contractor Involvement delivery of a new 89 MLD ceramic membrane plant with SIX/CEREMAC/ILCA membrane pilot. Programme development for pilot and main works, M&E design and build subcontract management, and compensation event quotation (£6m+) on defined cost. Site establishment included removal of 70,000m³ of overburden, with stakeholder engagement across Network Rail, the Environment Agency and the planning authority.

£6m+ CE quotations · 89 MLD plant delivered

Tophill Low WTW Recovery

Yorkshire Water

ClientYorkshire Water
Value£35m
ContractNEC
RoleProgramme Recovery

Engaged to recover a significantly distressed project involving new GAC, ISPS, lamella, sludge, ozone and polymer plant. Complete programme rebuild with client acceptance, commercial forecasting reconstruction, supply chain baselining, and successful challenge of previously rejected compensation events covering deleted weather provisions, ground conditions, instructed acceleration and access.

£4.6m+ CEs implemented · 12+ months EOT

Crossness & Greenwich STW/SPS

Thames Water

ClientThames Water
Value£35m
ContractNEC4 D&B
RoleProgramme Recovery

Recovery of a project with an identified 12+ month delay across new FEPS, LRPS, storm pump refurbishment and coarse screen penstock works. Complete programme rebuild to client acceptance, cost-to-complete with commercial mitigation, and NEC4 administration cascaded to the supply chain including early warning. CE strategy addressed late instructions, ground conditions, delayed access and contract data ambiguities.

Two EOT claims totalling £4m+ · 6 months recovered

Bellozanne STW

States of Jersey

ClientStates of Jersey
Value£65m
ContractNEC3
RoleProject Delivery

Project-wide management of a complete replacement sewage treatment works - inlet works, storm storage, settlement, activated sludge, UV, sludge storage and tanker import. Rebuild of a distressed programme to acceptance, management of a £24m subcontract package, cost-to-complete aligned to pain/gain, and daily collaborative planning against the critical path with an automated snagging system.

Distressed programme rebuilt · £24m package managed

Fleetwood STW Emergency Works

United Utilities

ClientUnited Utilities
Value£40m
ContractNEC
RoleProject Controls

Emergency response project replacing 500m of 1200mm GRP pipework and demobilising 2.5km of temporary pipework. Established compliant programme, cost control aligned to defined cost schedules, retrospective and forecast cost analysis in the absence of contractor submissions, and CEMAR-based compensation event procedures - with guidance to a junior contractor team on NEC time-bars and quotation assessment.

Controls established · CEMAR implemented

Birmingham Resilience Project

Severn Trent Water

ClientSevern Trent Water
Value£45m package
ContractNEC
RolePM

Design, installation, construction and commissioning of the treated water element of a £120m programme. Package included a 2.2m raw water inlet within a 2.44m segmental tunnel, a 13.5m deep cofferdam adjacent to a historic draw-off tower, and new sand-ballasted lamella and rapid gravity filter streams with full M&E package management.

£45m package delivered

Facing a Similar Challenge?

Let's discuss how Projjex can help recover or protect your project.

Get in Touch →