Church Wilne (Green Recovery)
Severn Trent Water
Early Contractor Involvement delivery of a new 89 MLD ceramic membrane plant with SIX/CEREMAC/ILCA membrane pilot. Programme development for pilot and main works, M&E design and build subcontract management, and compensation event quotation (£6m+) on defined cost. Site establishment included removal of 70,000m³ of overburden, with stakeholder engagement across Network Rail, the Environment Agency and the planning authority.